Wednesday 25 May 2016

Starting current of 3 phase motor

Divide each result by the motor voltage found on the nameplate. The resulting range is the inrush current range. The range given on the table is 8. There is no way to calculate the Starting Current or Locked Rotor Current (LRA) without more information! Single-phase or three - phase ?

Selection Tables – Three Phase Motors.

From the equivalent circuit of an induction motor it can be seen that the the expression of current is.

Three - phase squirrel-cage induction motors are used widely for various purposes. However, their starting currents are so large that they have to be estimated accurately and proper mea- sures should be taken to prevent hazards caused by them. So far, the starting currents of the three - phase squirrel-cage induction motor . Minimum fuse size for short-circuit protection of - phase motors.


The maximum size is determined by the requirements of the switchgear or overload relay. Unlike in DC motors , large current at starting is due to the absence of back emf. If an induction motor is directly . Inrush current , input surge current or switch-on surge is the maximal instantaneous input current drawn by an electrical device when first turned on. In stator resistance starting, external resistances are connected in series with each phase of stator winding during starting.


This causes voltage drop across the resistances so that voltage available across motor terminals is reduced and hence the starting current. The calculators below can be used to calculate electric motor amps , horsepower and - phase kVa. The objective of this starting metho which is used with three - phase induction motors , is to reduce the starting current.


In starting position, current supply to the stator windings is connected in star (Y) for starting. Non-inductive or slightly inductive loads, resistance furnaces. Slip-ring motors : starting , switching off . Squirrel-cage motors : starting , switching off motors during running (2).


A three - phase AC current incoming mains supply earthed as the neutral point. The kW per winding (single phase) has to be the total divided by 3. This inrush current lasts only until the motor shaft has reached its rated spee so it is typically of very short duration, perhaps less than one second.

No comments:

Post a Comment

Note: only a member of this blog may post a comment.

Popular Posts